Highway Works and Road Closure Notices

 

 
 



 

TEMPORARY ROAD CLOSURES –  Operation Resilience

As part of the programme of works being undertaken by Operation Resilience, we will be undertaking road resurfacing in Fullers Vale, Headley.

The works are programmed to start on 4th February 2012 for one day of preparatory works, and then a further 2 days for surfacing beginning 9th February 2012. In order to undertake the works safely it will be necessary to close the road between 0900hrs until 1630hrs each day. A plan of the diversion route is attached to the following link http://g.co/maps/x6c64

Please note that following further consultation with our contractor, the works will now be extended one further day to include a closure on Monday 13th Feb 2012. The road will be open over the weekend.

Should you have any questions or require further information please contact the Operation Resilience team on 01730 263631 or email operation.resilience@hants.gov.uk
Regards

Christopher Doggett
Advanced Technician - Operation Resilience