2009
Construct new southbound carriageway between the Spaniard and Hazel Grove Started
Complete tunnel excavation and primary lining  Complete
Excavate deep cutting north of Hazel Grove Nearing Completion
Construct Miss James Footbridge Foundations Started
Construct tunnel service buildings Substantially complete
Complete embankment and bunds in Boundless Valley Embankments Complete
Carry out tunnel invert  lining works Well under way in South Tunnel
2010
Install drainage for new A3 Started
Lay pavement for new A3 Planned
Carry out mechanical and electrical installation works along new A3 Planned
Carry out landscaping and planting Planned
Install mechanical and electrical systems in the tunnel Planned
Open new dual carriageway from the Spaniard to Hazel Grove junction Planned
2011
Test tunnel mechanical and electrical systems Planned
Open new A3 Planned
Carry out alterations to existing A3 Planned
Start landscaping and planting Planned
2012
Complete landscaping and planting  Planned